sheet metal fabrication

5 November 2014

Steel stock unit complete

5 November 2014, Comments: 0

SMS are happy to announce that the Steel Stock unit is now complete, racking installed and ready to use. The insulated roof will help […]


30 October 2014

Assembling on 3rd day sees panelling installed

30 October 2014, Comments: 0

It is the 3rd day of installing panelling onto the building, and it provides a view of how spacious the interior is becoming. The […]


29 October 2014

2nd Day of Assembly

29 October 2014, Comments: 0

Contractors have been installing the insulated roof on 2nd day of assembly. The roof has an air filled cavity to keep the building temperature […]


28 October 2014

End of 1st day of assembling building

28 October 2014, Comments: 0

Steelwork for building completed before end of 1st day as promised. Tomorrows plan includes the insulated roof being fastened onto framework and possibly panelling […]


27 October 2014

Assembly of building steelwork commences.

27 October 2014, Comments: 0

  Monday 27th October 2014, and delivery of steel work for building has been received on site. Contractors Aganto begin erecting steel framework, and […]


20 October 2014

Car Park 90% complete.

20 October 2014, Comments: 0

Over the weekend of 18th & 19th October contractors complete the car park with a layer of tarmac, this is to be finished off […]